If the optimistic time is 3,the most likely time is 5,and the pessimistic time is 7,then the expected time is
A) 6)
B) 5)
C) 15.
D) 4)
Correct Answer:
Verified
Q60: Dependencies involving relationships between the project and
Q61: A method of planning and managing projects
Q62: Which of the following includes activities performed
Q63: Shortening an activity is called
A)float.
B)crash.
C)reduction.
D)smoothing.
Q64: The ratio of rise and run of
Q66: The completion time having the highest probability
Q67: In CCPM,a finite amount of time that
Q68: An overall management philosophy introduced by Goldratt
Q69: What is PDM? Why is it useful?
Q70: The longest time that an activity might