 Which of the following is true of the project life cycle?
A) In the early phases of a project life cycle, resource needs are usually lowest.
B) In the later phases of the project life cycle, the level of uncertainty is usually the highest.
C) It is much more expensive to make major changes to a project during the earlier phases than the latter phases.
D) More resources are usually needed during the initial phases of a project than during the middle or final phases.

 Which of the following is true of the project life cycle?


A) In the early phases of a project life cycle, resource needs are usually lowest.
B) In the later phases of the project life cycle, the level of uncertainty is usually the highest.
C) It is much more expensive to make major changes to a project during the earlier phases than the latter phases.
D) More resources are usually needed during the initial phases of a project than during the middle or final phases.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents