Which Activity Is a Part of the Scrum Planning Process

Question 50

Multiple Choice
 Which activity is a part of the Scrum planning process?
A) Determining how many sprints will compose each release
B) Demonstrating the product during a sprint review meeting
C) Completing tasks each day during sprints
D) Creating sprint backlog

 Which activity is a part of the Scrum planning process?


A) Determining how many sprints will compose each release
B) Demonstrating the product during a sprint review meeting
C) Completing tasks each day during sprints
D) Creating sprint backlog