Question 22

Multiple Choice
 Which process involves working with stakeholders to create the document that formally authorizes a project?
A) Developing the project charter
B) Developing the preliminary project scope statement
C) Developing the project management plan
D) Performing integrated change control

 Which process involves working with stakeholders to create the document that formally authorizes a project?


A) Developing the project charter
B) Developing the preliminary project scope statement
C) Developing the project management plan
D) Performing integrated change control

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents