In project schedule management, which process generates the main outputs of an activity list, activity attributes, and a milestone list?
A) sequencing activities
B) defining activities
C) resource estimating activities
D) estimating activity durations
Correct Answer:
Verified
Q29: Which process in project schedule management involves
Q30: A backward pass through the network diagram
Q31: What is the first process involved in
Q32: In project schedule management, which process primarily
Q33: The final process in project schedule management
Q35: The critical path on a project can
Q36: Which term is used for a significant
Q37: In project schedule management, which is an
Q38: The technique of fast tracking can result
Q39: The main disadvantage of crashing is that