At a burst point,______.
A) you have a node with two or more successors
B) the largest preceding EF becomes the ES for that node
C) you have a node with two or more predecessors
D) the largest preceding ES becomes the LF for that node
Correct Answer:
Verified
Q60: Which of the following is a limitation
Q61: "Crashing" a project _.
A)is speeding up a
Q62: A critical path consists of _.
A)activities that
Q63: At a merge point,_.
A)the largest preceding EF
Q64: The backward pass _.
A)starts at the end
Q66: In considering the impact supply chains have
Q67: Which of the following statements is true
Q68: Which of the following is an appropriate
Q69: Which is the critical path in the
Q70: In managing projects in supply chains,working with