Which of the following is an approach to managing the risk that a contractor may not complete a complex project properly?
A) Require the contractor to operate it for a while to demonstrate everything is functioning as it should.
B) Award the same project to multiple contractors to improve the chances that one of the contractors will successfully finish the project.
C) Guarantee that key employees from the contractor will have high-paying jobs with the primary company on successful completion of the contract.
D) Recruit personnel on behalf of the contractor to ensure that high-quality resources are deployed in the project.
Correct Answer:
Verified
Q89: Which of the following is the final
Q90: Which of the following is NOT a
Q91: The debate about "jobs versus the environment"
Q92: A company can acquire ISO 9001 certification
Q93: Which of the following is NOT a
Q95: The groups that lobby against fossil fuels
Q96: If the delivery of goods or services
Q97: Which of the following is NOT an
Q98: In contracting a project to a third-party,the
Q99: If the delivery of goods or services
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents