Which Planning Approach Is Used When Management Calculates the Resource

Question 22

Multiple Choice

Which planning approach is used when management calculates the resource requirement for each individual set of products or services and then combines to get an overall picture of resource requirement?


A) bottom-up
B) top-down
C) aggregate
D) independent

Correct Answer: