Question 23

Multiple Choice

A scheduling process used to determine the approximate completion time for each job,the capacity required in each time period by beginning with the current date for those jobs that have known processing requirements,and loading the jobs forward in time is called ______.


A) current-date scheduling
B) forward scheduling
C) due-dates scheduling
D) backward scheduling