Determine the sequence of job processing using the critical ratio method for the jobs listed in the following table.Assume today's date is 20.
A) E-C-A-B-D
B) E-C-A-D-B
C) E-A-B-C-D
D) B-A-C-D-E
Correct Answer:
Verified