Purple Airlines has ordered 30 small jets from its supplier.The supplier has estimated the first aircraft will require 350 days of direct labor to manufacture and assemble.Based on past experience,the supplier estimates the learning curve to be 75%.Estimate the average number of days of direct labor for all 30 jet aircrafts.
A) 231.43 days
B) 121.43 days
C) 133.54 days
D) 156.43 days
Correct Answer:
Verified
Q17: Understanding learning curves will enable procurement specialists
Q18: Assume that it takes 100 hours to
Q19: Learning curves are of little use for
Q20: In general,it is more challenging to apply
Q21: Consider a programmer required to complete four
Q23: The first unit produced in a process
Q24: Which of the following statements is FALSE
Q25: Which of the following metrics is used
Q26: ABC Hospital completed its first transplant,and the
Q27: A construction firm wants to estimate the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents