In project management,PERT (program evaluation and review technique) ______.
A) uses a weighted average of optimistic,pessimistic,and most likely estimates to calculate the expected duration for an activity
B) uses a deterministic approach to calculate the expected duration for an activity
C) use a simple average of optimistic,pessimistic,and most likely estimate to calculate the expected duration for an activity
D) uses a most likely estimate to calculate the expected duration for an activity
Correct Answer:
Verified
Q22: The slope for each activity gives _.
A)combinations
Q23: In considering whether we should crash a
Q24: Projections about how much the project will
Q25: Which one of the following is a
Q26: Which of the following correctly pairs the
Q28: Project overhead costs _.
A)are also known as
Q29: The proportion of the total budget allocated
Q30: The SPI is _.
A)the stochastic performance index
B)the
Q31: The cost of the project is given
Q32: The work breakdown structure identifies _.
A)each of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents