If the standard deviation is 3.5,the Z value is 1.0,and the expected date of completion is 30 weeks,then the due date for project completion is ______.
A) 33.5 weeks
B) 41.5 weeks
C) 21.95 weeks
D) 38.55 weeks
Correct Answer:
Verified
Q87: If the standard deviation is 3.4,the Z
Q88: If the most optimistic time for completing
Q89: If the standard deviation is 6.2,the Z
Q90: If the most optimistic time for completing
Q91: If the most optimistic time for completing
Q93: If the standard deviation is 2.7,the Z
Q94: If the most optimistic time for completing
Q95: If the standard deviation is 4.5,the Z
Q96: If the most optimistic time for completing
Q97: If the most optimistic time for completing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents