In capacity requirements planning,we project or estimate ______.
A) the level of demand for each product that we are planning to produce
B) resource requirements for labor,equipment,and other production needs
C) the quantity of finished product to be stored in different distribution centers
D) the activities at each workstation to balance workload
Correct Answer: