Zero,Inc.agreed to build Millie a storage building for $8,000.After beginning the project,Zero realized that it could not complete the job and make a profit.Zero demanded $9,500 to complete the building.Millie agreed to pay the $9,500.When the project was complete,Millie tendered $8,000 to Zero for the job.If Zero sues Millie for the remaining $1,500,
A) Zero will win because there was consideration for the additional $1,500.
B) Zero will win because Millie had a preexisting duty to pay any additional amounts.
C) Zero will lose because there was no legal consideration to support the additional $1,500.
D) Zero will lose because the UCC does not require consideration to modify an existing contract.
Correct Answer:
Verified
Q21: Regarding consideration,an act occurs when a person
A)complies
Q22: Jamie is building a house on her
Q23: Yolanda was shoveling snow from her sidewalk,and
Q24: Bernie owes an undisputed amount to Wilde's
Q25: If Becky promises not to drink alcohol
Q27: Upon graduating from college,Kathy announced her plans
Q28: If someone provides a service that he
Q29: An agreement to settle a debt for
Q30: Mid-American Oil had a contract with NSB
Q31: What is an output contract?
A)A contract in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents