A(n) _____ lists the completion time of a project on the x-axis and all the activities on the y-axis,which allows the systems analyst to monitor the progress of the project and detect any delay in the daily operation of the project.
A) work breakdown structure
B) event chain diagram
C) Gantt chart
D) risk register
Correct Answer:
Verified
Q45: During the _ of the systems development
Q53: _ is a series of well-defined phases
Q58: One shortcoming of rapid application development (RAD)is
Q64: Discuss the five capabilities of computer-aided systems
Q68: Explain the importance of the formation of
Q69: Describe how information systems are implemented using
Q71: A _ is a tool used in
Q76: _ is the approach where an organization's
Q76: Discuss the four steps involved in prototyping.
Q85: _ focuses on setting a minimum number
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents