A(n)_____ Lists the Completion Time of a Project on the X-Axis

Question 80

Multiple Choice

A(n) _____ lists the completion time of a project on the x-axis and all the activities on the y-axis,which allows the systems analyst to monitor the progress of the project and detect any delay in the daily operation of the project.


A) work breakdown structure
B) event chain diagram
C) Gantt chart
D) risk register

Correct Answer: