All of the following activities are appropriate upon completion of risk response planning EXCEPT:
A) The risk register should be updated to reflect the risk response strategies.
B) The risk register should be baselined after planning is completed, and should not be updated once the project is in flight.
C) The project plan should be updated to reflect any changes to the project schedule, budget or resource assignments.
D) A single person should be assigned as the owner of each risk.
Correct Answer:
Verified
Q35: All of the following describe an appropriate
Q36: Project teams can often identify risks by
Q37: Which of the following quantitative risk analysis
Q38: Which of the following accurately describes risk
Q39: All of the following are benefits that
Q40: Which of the following activities illustrates a
Q42: Identify and describe three risk identification techniques.What
Q43: Identify five common project risk strategies employed
Q44: All of the following activities illustrate a
Q45: How might you approach the prioritization of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents