The Procurement Management Plan

Question 29

Multiple Choice

The procurement management plan: 


A)  describes how the procurement division will be managed. 
B)  describes how supply chain partners will be managed. 
C)  describes how a project team will acquire goods and services from outside the performing organization. 
D)  describes how sellers will be audited by the procurement team.

Correct Answer:

verifed

Verified