When Part of a Progress Payment for Construction Is Withheld

Question 46

Multiple Choice
When part of a progress payment for construction is withheld until final settlement of the contract, what account is credited?

When part of a progress payment for construction is withheld until final settlement of the contract, what account is credited?


A) Encumbrances.
B) Appropriations.
C) Contracts Payable-Retained Percentage.
D) Construction Expenditures.

Correct Answer: