Prepare Journal Entries for the Following Related Transactions in the Fund

Question 81

Essay
Prepare journal entries for the following related transactions in the fund and activity journals affected: (If no entry is required for a transaction/event, select "No Journal Entry Required" in the first account field.)
1. A capital projects fund issued $5,000,000, 4 percent bonds for $5,050,000 to finance improvements of a park. Premiums received are to be used to service the debt issue.
2. The Parks and Recreation Special Revenue Fund transferred $250,000 for use in construction.
3. A construction contract was awarded in the amount of $5,200,000.
4. A bill was received from the contractor for $2,600,000.
5. The contractor's bill is paid, and 5% retainage is withheld.
6. The park renovations were completed and the final bill of $2,600,000 was received. The contractor's bill and retainages are approved for payment in full. Total construction expenditures were allocated as follows: $5,000,000 to building, and the remainder to equipment.
7. The capital projects fund temporary accounts were closed, and the capital projects fund was closed by transferring remaining funds to the debt service fund for use in debt repayment.

Prepare journal entries for the following related transactions in the fund and activity journals affected: (If no entry is required for a transaction/event, select "No Journal Entry Required" in the first account field.)
1. A capital projects fund issued $5,000,000, 4 percent bonds for $5,050,000 to finance improvements of a park. Premiums received are to be used to service the debt issue.
2. The Parks and Recreation Special Revenue Fund transferred $250,000 for use in construction.
3. A construction contract was awarded in the amount of $5,200,000.
4. A bill was received from the contractor for $2,600,000.
5. The contractor's bill is paid, and 5% retainage is withheld.
6. The park renovations were completed and the final bill of $2,600,000 was received. The contractor's bill and retainages are approved for payment in full. Total construction expenditures were allocated as follows: $5,000,000 to building, and the remainder to equipment.
7. The capital projects fund temporary accounts were closed, and the capital projects fund was closed by transferring remaining funds to the debt service fund for use in debt repayment.

Correct Answer:

verifed

Verified

1.
blured image
\[\begin{array} { | l | r | r | } ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents