The order of the steps in the SAP R/3 production planning process are:
A) Sales Forecasting,Demand Management,Purchasing,Sales and Operations Planning,MRP,Detailed scheduling,Production
B) Sales Forecasting,Demand Planning,Detailed scheduling,Purchasing,Demand Management,MRP,Production
C) Sales and Operations Planning,Sales Forecasting,MRP,Purchasing,Demand Management,Detailed scheduling,Production
D) Sales Forecasting,Sales and Operations Planning,Demand Management,MRP,Purchasing,Detailed scheduling,Production