In earned value Analysis,the 50-50 rule assumes that __________.
A) 50 percent is earned when the task is half done and 50 percent is earned at completion
B) 50 percent is earned when the task begins and 50 percent is earned at completion
C) 50 percent is earned when the task begins and 50 percent is earned at the halfway stage
D) 50 percent is earned when the project is planned and 50 percent is earned when the project is over
Correct Answer:
Verified
Q29: In earned value analysis,the _ is computed
Q30: If EV = $500,AC = $475,PV =
Q31: Which of the following conventions has the
Q32: In earned value analysis,if the cost variance
Q33: If EV = $500,AC = $450,PV =
Q35: _ can often give the project manager
Q36: EV - PV = _.
A)SV
B)CV
C)CPI
D)TV
Q37: If CSI is less than 1,it is
Q38: In earned value analysis,(CPI)(SPI)= _.
A)CV
B)TPI
C)CSI
D)SV
Q39: Which of the following is not a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents