Using the assembly-line balancing procedure, which of the following is the required cycle time in minutes per unit if the daily production time is 480 minutes and the required daily output is 50 units?
A) 0.104
B) 50
C) 9.6
D) 480
E) Cannot be determined from the information above
Correct Answer:
Verified
Q7: In balancing an assembly line, workstation cycle
Q20: The assembly-line balancing procedure determines the precedence
Q21: For the purposes of assembly-line balancing, the
Q21: The essential issue in satisfying customers in
Q22: A project layout is characterized by a
Q23: A process map shows the physical location
Q25: Little's law states that supply chain processes
Q26: Workstation cycle time is the time between
Q27: Using the assembly-line balancing procedure, which of
Q29: If the sum of the task times
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents