simple project listing of five activities,their predecessors,and their respective time estimates are presented below:
Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project) ?
A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days
Correct Answer:
Verified
Q43: You have just been assigned to oversee
Q45: An advantage of a pure project where
Q52: company must perform a maintenance project consisting
Q52: Some of the advantages of a functional
Q53: simple project listing of five activities,their predecessors,and
Q54: For an activity in a CPM analysis,the
Q56: simple project listing of five activities and
Q59: For an activity in a CPM analysis
Q64: You know when you have arrived at
Q67: You have just performed a CPM analysis
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents