In a project analysis using three time estimates with more than one critical path existing, how does the project manager decide which variances to use in arriving at the probability of meeting the project due date?
A) The project manager averages the variances and uses that.
B) The project manager uses the smallest variance in order to get the highest probability of on-time completion.
C) The project manager uses the variances considered most correct.
D) The project manager uses the largest variances in order to understate the probability of on-time completion.
E) The project manager uses the most likely estimate plus the amount of slack time in the project.
Correct Answer:
Verified
Q43: You have just been assigned to oversee
Q59: A simple project listing of five activities
Q62: You have collected the data for a
Q63: In CPM analysis, it is generally expected
Q65: You have just used the network planning
Q65: You have just used the network planning
Q67: You have just performed a CPM analysis
Q67: Below are the data for a Time-Cost
Q68: You have the following time and cost
Q69: Below are the data for a Time-Cost
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents