Which implementation assigns a small group of people to use the new system until it is verified to work correctly; then the remaining users migrate to the new system?
A) parallel implementation
B) plunge implementation
C) pilot implementation
D) phased implementation
Correct Answer:
Verified
Q194: Which high-level programming language uses C+ and
Q195: Which implementation uses both the legacy system
Q196: What is a group of people who
Q197: What tests individual units or pieces of
Q198: What occurs when programmers test the system
Q200: Which implementation discards the legacy system and
Q202: What is an activity-based process in which
Q203: Which implementation installs the new system in
Q204: What makes system changes to reduce the
Q220: Which methodology provides a framework for breaking
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents