What are the three primary variables (or triple constraints) in any project?
A) time, cost, expense
B) time, expense, requirements
C) time, cost, scope
D) time, cost, quality
Correct Answer:
Verified
Q258: What measures how well a solution can
Q259: Which of the following are tangible benefits?
A)improved
Q260: What is a markup language for documents,
Q261: What is any measurable, tangible, verifiable outcome,
Q262: What is an internal department that oversees
Q264: Who are individuals and organizations actively involved
Q265: What represents key dates when a certain
Q266: What are project constraints?
A)specific factors that can
Q267: What is a status report?
A)difficult to quantify
Q268: Who is the person or group who
Unlock this Answer For Free Now!