What is the critical path?
A) the path from resource to task that passes through all critical components of a project plan
B) the path between tasks to the project's finish that passes through all critical components of a project plan
C) the sequence of activities that determine the earliest date by which the project can be completed
D) the path from start to finish that passes through all the tasks that are critical to completing the project in the longest amount of time
Correct Answer:
Verified
Q98: In a Gantt chart, tasks are listed
Q286: What are project objectives?
A)quantifiable criteria that must
Q287: An organization must identify what it wants
Q288: What is an arrangement by which one
Q289: Which of the following is not a
Q291: What is the logical relationship that exists
Q292: What is it called when a company
Q293: What type of chart typically displays the
Q294: What do SMART criteria for successful objective
Q295: What is a simple bar chart that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents