Elijah is a warehouse production manager who has been assigned a complex project that might result in lengthy delays.In order to coordinate all aspects of the production process,Elijah has created a(n) ________ chart.
A) ISO
B) FMS
C) Gantt
D) PERT
Correct Answer: