Champion Cooling has just signed a contract to assemble window air conditioners for another company.The list of tasks,including time requirements and immediate predecessors,follows.Initially,the plan was to make 300 units in an eight hour day but as the summer months approach,Champion Cooling finds themselves far behind in total production.They wish to reconfigure their production line in order to produce maximum output.What should their takt time be?
A) 5
B) 6
C) 7
D) 10
Correct Answer:
Verified
Q40: Draw the product-process matrix and discuss the
Q44: The process design team at a manufacturer
Q46: In a service blueprint, the two layers
Q47: The _ includes all the value-added physical
Q49: As the degree of customer contact decreases,more
Q67: Use this scenario for the following
Q78: Define the terms front room and back
Q80: Use this scenario for the following
Q82: A manager deciding where six departments could
Q98: Cycle time is the sum of all
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents