Use this scenario for the following question(s) .
The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
-Refer to the scenario above. What is the takt time?
A) 53.3 seconds
B) 67.5 seconds
C) 75.8 seconds
D) 90 seconds
Correct Answer:
Verified
Q58: Service operations compete and position themselves in
Q59: An independent study for a graduate student
Q60: In a service blueprint, the line of
Q61: The process design team at a
Q62: Use this scenario for the following
Q64: Name a service business that relies heavily
Q65: Use this scenario for the following
Q66: The table depicts a production line
Q67: Use this scenario for the following
Q68: Name two restaurants that score differently on
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents