The table depicts a production line that has been balanced with a takt time of 2 minutes.If you could hire another six workers,which of these systems would result in the highest output rate?
A) simply duplicating the existing line so you had two lines doing exactly the same thing
B) assigning one worker to each activity and creating a single twelve station production line
C) keeping the existing balance and assigning three workers to stations 1, two workers to station 2, two workers to station 3, one worker to station 4, two workers to station 5, and two workers to station 6
D) you would be indifferent between alternatives a and b
Correct Answer:
Verified
Q63: Use this scenario for the following
Q65: Use this scenario for the following
Q65: With the backyard poultry craze unleashing a
Q67: These three tables show the floor layout
Q69: The table depicts a production line that
Q71: The table depicts an production line that
Q72: The process design team at a manufacturer
Q72: Use this scenario for the following
Q84: Use this scenario for the following
Q100: A collection of different departments must be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents