Use this scenario for the following question(s) .
With the backyard poultry craze unleashing a tidal wave of municipal code proposals, Chickenverks is poised to capitalize on the sudden demand for chicken tractors. The portable henhouses they have designed can be assembled in 10 basic steps, each with a required time and predecessor as shown in the table. There are 8 productive hours available in a day and the manufacturer wishes to produce 40 units per hour.
-Refer to the scenario above. Balance the line according to the longest operation rule. What is the efficiency of your line balance?
A) 85.66%
B) 90.28%
C) 88.14%
D) 83.88%
Correct Answer:
Verified
Q80: Use this scenario for the following
Q81: With the backyard poultry craze unleashing
Q82: A manager deciding where six departments could
Q83: The only way to ensure that a
Q84: Use this scenario for the following
Q86: The process design team at a
Q87: A manufacturer needs to produce 300
Q88: Takt time sets the upper limit on
Q89: Regardless of the number of tasks or
Q90: The maximum allowable time between completions of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents