At current prices and a 13 percent cost of capital, a project's NPV is $100,000.By what minimum amount must the initial cost of the project decrease (revenues will be unchanged) before you would prefer to wait two years before investing?
A) $21,685
B) $26,000
C) $27,690
D) $29,380
Correct Answer:
Verified