What is the NPV of a project that costs $100,000, provides $23,000 in cash flows annually for six years, requires a $5,000 increase in net working capital, and depreciates the asset straight line over six years while ignoring the half-year convention? The discount rate is 14%.
A) -$15,561
B) -$13,283
C) $13,283
D) $15,561 Net Present Value = 23,000
Correct Answer:
Verified
Q2: Sunk costs do not affect project NPV.
Q8: Capital budgeting analysis focuses on profits as
Q12: As a project comes to its end,there
Q16: Opportunity costs are evaluated for investment decisions
Q19: If a project permits a reduction in
Q20: When you finance a project partly with
Q40: What rate of nominal growth is expected
Q77: Assuming that an asset has been fully
Q80: For a profitable firm in the 30%
Q86: A project that increased sales was accompanied
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents