What is the NPV for the following project cash flows at a discount rate of 15 percent? CF0 = ($1,000) , CF1 = $700, CF2 = $700.
A) ($308.70)
B) ($138.00)
C) $138.00
D) $308.70 NPV = $700
Correct Answer: