Solved

If Changing Discount Rates from the Company Cost of Capital

Question 41

Multiple Choice

If changing discount rates from the company cost of capital to the project cost of capital changes NPV from negative to positive, then the project should use the:


A) Company cost of capital and be accepted
B) Company cost of capital and be rejected
C) Project cost of capital and be accepted
D) Project cost of capital and be rejected

Correct Answer: