What are the immediate predecessors of activity D in this network?
A) A, B, C
B) B, C
C) E, F
D) E, G, H
Correct Answer:
Verified
Q1: How many paths are there in the
Q3: What is the earliest start time for
Q4: What is the latest finish time for
Q7: What are the immediate successors of activity