As the 80th change order floated across his desk,the project manager wished that he had kept the first 79.What money he had saved in scrap paper might well be lost in charges that could never be recouped from the client."What I need is better:
A) Trend monitoring," muttered the manager.
B) Configuration control," sighed the manager.
C) Specification control," fumed the manager.
D) Document control," whimpered the manager.
Correct Answer:
Verified
Q64: Systems for monitoring the project's scope,schedule,and costs
Q65: Organizational breakdown structure (OBS)allows companies to:
A)Assign the
Q66: List any five important points to remember
Q67: What is a scope statement and what
Q68: What is hierarchy among the deliverable,work package,subdeliverable,and
Q70: Provide an example of work breakdown structure
Q71: Procedures that monitor emerging project scope against
Q72: Create a 4×4 responsibility assignment matrix as
Q73: A work package may be composed of
Q74: A work package may consist of more
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents