The primary action during a configuration review is to:
A) Develop a breakdown of the project to the necessary level of definition.
B) Identify the specifications of the components of the breakdown and of the total project.
C) Meet with all the project stakeholders to agree to the current project definition.
D) Change the specifications last obtained by a process change control to match what people think it should be.
Correct Answer:
Verified
Q79: In order to allocate costs more precisely,a
Q80: The scope baseline is a document that
Q81: The status accounting step of configuration management
Q82: The BEST time to establish reasonable controls
Q83: A priori consideration of information needs is
Q85: Which step in project management requires project
Q86: What is the purpose of controls? Describe
Q87: What is configuration management and why is
Q88: Closeout documentation that follows a formal reporting
Q89: If viewed from a flow standpoint,the stage
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents