Which of these statements about the project risk analysis and management program is BEST?
A) Risk management is best handled using an ad hoc approach.
B) If a choice between accepting and transferring risk presents itself,risk should be transferred.
C) The project manager should choose a small subset of all risk management tools.
D) Multiple approaches to risk management should be integrated into a coherent,synthesized approach.
Correct Answer:
Verified
Q92: Allocation of client risks to named individuals
Q93: Every one of the nine phases of
Q94: The PRAM model for risk management proposes
Q95: The PRAM step that occurs while the
Q96: The PRAM model for risk management proposes
Q97: What are the two types of contingency
Q98: What does change management accomplish and what
Q100: At each phase,the project risk analysis and
Q101: What is the PRAM methodology and what
Q102: Pick any three steps in the PRAM
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents