Solved

The First Phase of a Comprehensive Project Risk Assessment Should

Question 88

Multiple Choice

The first phase of a comprehensive project risk assessment should be:


A) To assess the specific sources of risk at the outset of the project,including the need to fashion appropriate responses.
B) To make sure the project is well defined,including all deliverables,statement of work,and project scope.
C) To develop reasonable estimates of the impacts on the project of both the identified risks and the proposed solutions.
D) To produce a project risk management plan that proactively offers risk mitigation strategies for the project as needed.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents