The new bridge would require 14 piers to support it and it was known that each time a pier is sunk into the harbor it would take 30 man hours of labor at $50 per hour.An activity-based costing of the entire pier system results in a total labor cost of:
A) $19,500.
B) $21,000.
C) $22,500.
D) $24,000.
Correct Answer:
Verified
Q68: Input is received from an organization's management
Q69: The project management research in brief titled
Q70: What's the relationship between WBS,scheduling,and budgeting?
Q71: Describe any three reasons that cost overruns
Q72: The new artisanal greenhouse would require 700
Q74: A budget containing disaggregated figures across the
Q75: Which of the following is NOT contained
Q76: Top-down budgeting,where input is gathered directly from
Q77: The project plan is supported by:
A)The work
Q78: Activity-based costing and bottom-up budgeting share the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents