What Is the Total Project Budget for Design in This

Question 85

Multiple Choice

What is the total project budget for design in this time-phased budget?  Activity  July  August  Septernber  October  Novernber  RFP 34,721 Aralysis 11,04933,65534,388 Pesiggn 33,71834,47426,75936,328 Codirg 7,71334,90540,244 Testing 40,916896 Trairing 20,9589,327 Roll-Out 8,186\begin{array} { | l | l | l | l | l | l |} \hline \text { Activity } & \text { July } & \text { August } & \text { Septernber } & \text { October } & \text { Novernber } \\\hline \text { RFP } & 34,721 & & & & \\\hline \text { Aralysis } & 11,049 & 33,655 & 34,388 & & \\\hline \text { Pesiggn } & 33,718 & 34,474 & 26,759 & 36,328 & \\\hline \text { Codirg } & & 7,713 & 34,905 & 40,244 & \\\hline \text { Testing } & & & & 40,916 & 896 \\\hline \text { Trairing } & & & & 20,958 & 9,327 \\\hline \text { Roll-Out } & & & & & 8,186 \\\hline\end{array}


A) $131,279
B) $155,330
C) $124,688
D) $146,983

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents