Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?
A) 3
B) 5
C) 7
D) 9
Correct Answer:
Verified
Q66: Q67: Use the information in the table Q68: A gentleman farmer maniacally works on Q69: Compute early and late start and finish Q70: The amount of time an activity may Q72: Construct a network using the information Q73: A project has the precedence requirements Q74: Use the information in the table Q75: The least amount of float is found: Q76: Use the information in the table![]()
A)In
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents