The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:
A) Delay.
B) Float.
C) Late start.
D) Late finish.
Correct Answer:
Verified
Q65: Phoebe B.Beebee is constructing a canal
Q66: Q67: Use the information in the table Q68: A gentleman farmer maniacally works on Q69: Compute early and late start and finish Q71: Project Test Bank is composed of Q72: Construct a network using the information Q73: A project has the precedence requirements Q74: Use the information in the table Q75: The least amount of float is found: