A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides to represent a few activities by a hammock activity.Which is a legitimate hammock activity for this project?
A) Combine activities A,B,C
B) Combine activities B,E,H
C) Combine activities E,F
D) Combine activities G,H,I
Correct Answer:
Verified
Q94: What is the float start time
Q95: An MBA student laboriously calculated the
Q96: What is the slack time for
Q97: A gentleman farmer maniacally works on