Question 60

Essay

What is the cost to finish this project (all activity durations are in weeks and costs in US dollars)as quickly as possible?
 Normal  Minimum  Normal  Activity  Predecessor  Time  Time  Cost  Crash Cost A121010001500 B  A 5312001950 C  A 9715002100 D  B, C 141018002100 E  B 4314001875 F  D 9810001450 G  E 757001200 H  F, G 11820003000 I  H 8611001700\begin{array}{|l|l|l|l|l|l|} \hline &&\text { Normal }&\text { Minimum }&\text { Normal }\\ \text { Activity } & \text { Predecessor } & \text { Time } &\text { Time } & \text { Cost }&\text { Crash Cost }\\ \hline \mathbf{A} & & 12 & 10 & 1000 & 1500 \\\hline \text { B } & \text { A } & 5 & 3 & 1200 & 1950 \\\hline \text { C } & \text { A } & 9 & 7 & 1500 & 2100 \\\hline \text { D } & \text { B, C } & 14 & 10 & 1800 & 2100 \\\hline \text { E } & \text { B } & 4 & 3 & 1400 & 1875 \\\hline \text { F } & \text { D } & 9 & 8 & 1000 & 1450 \\\hline \text { G } & \text { E } & 7 & 5 & 700 & 1200 \\\hline \text { H } & \text { F, G } & 11 & 8 & 2000 & 3000 \\\hline \text { I } & \text { H } & 8 & 6 & 1100 & 1700 \\\hline \end{array}

Correct Answer:

verifed

Verified

The initial project duration is 63 weeks...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents