Mick has a project consisting of eight activities (listed in the table with durations and precedence requirements)to complete.He assigned his intern Guinness to sketch a network diagram in AOA and Guinness produced the sketch shown below.Discuss any issues with the apprentice's diagram.
 Activity  Activity time  Predecessar A6B8C5 A D9 A, B E12 AF11D,EG6C,F\begin{array} { | l | l | l|} \hline \text { Activity } & \text { Activity time } & \text { Predecessar } \\\hline\mathrm { A } & 6 & \\\hline\mathrm { B }& 8 & \\\hline \mathrm { C } & 5 & \text { A } \\\hline \mathrm { D } & 9 & \text { A, B } \\\hline \mathrm { E } & 12 & \mathrm {~A} \\\hline \mathrm { F } & 11 & \mathrm { D } , \mathrm { E } \\\hline \mathrm { G } & 6 & \mathrm { C } , \mathrm { F } \\\hline\end{array}  Mick has a project consisting of eight activities (listed in the table with durations and precedence requirements)to complete.He assigned his intern Guinness to sketch a network diagram in AOA and Guinness produced the sketch shown below.Discuss any issues with the apprentice's diagram.   \begin{array} { | l | l | l|}  \hline \text { Activity } & \text { Activity time } & \text { Predecessar } \\ \hline\mathrm { A } & 6 & \\ \hline\mathrm { B }& 8 & \\ \hline \mathrm { C } & 5 & \text { A } \\ \hline \mathrm { D } & 9 & \text { A, B } \\ \hline \mathrm { E } & 12 & \mathrm {~A} \\ \hline \mathrm { F } & 11 & \mathrm { D } , \mathrm { E } \\ \hline \mathrm { G } & 6 & \mathrm { C } , \mathrm { F } \\ \hline \end{array}

Correct Answer:

verifed

Verified

There is a need for only one d...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents