XYZ project organization has one workstation that is capable of generating the drawings that their clients study before accepting XYZ's bid.XYZ is currently in the midst of three proposal projects and knows exactly when it will need to use the workstation.All other work to be done,both before and after the workstation is used,is scheduled such that it flows to the workstation and keeps it busy.Resources used after this step are less critical;so while the subsequent work and resources are important,they aren't viewed with the same reverence as the workstation.This is an example of:
A) Identifying a constraint.
B) Elevating a constraint.
C) Subordinating a system.
D) Exploiting a constraint.
Correct Answer:
Verified
Q35: Extreme programming advocates a large development staff,several
Q36: Which of these is a drawback for
Q37: Refactoring is the continuous process of streamlining
Q38: Wayne and Garth are engaged in XP
Q39: A product backlog is the final list
Q41: Your next project consists of 5 consecutive
Q42: Which of the following statements about CCPM
Q43: What are the five steps behind the
Q44: What is the difference between the critical
Q45: Your boss catches you at the water
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents